MINNEAPOLIS (AP) — The developers of a long-delayed copper-nickel mining project in northeastern Minnesota announced Wednesday that they plan to conduct a series of studies over the next year on potential ways to improve environmental safeguards and make the mine more cost- and energy-efficient, which could lead to significant changes to the design.
The plan is for a $1 billion open-pit mine near Babbitt and processing plant near Hoyt Lakes that would be Minnesota’s first copper-nickel mine and produce minerals necessary for the clean energy economy. It is a 50-50 joint venture between Swiss commodities giant Glencore and Canada-based Teck Resources. The project was renamed NewRange Copper Nickel last year but it is still widely known by its old name, PolyMet. The project has been stalled for several years by court and regulatory setbacks, but company officials say they are still moving ahead with preparations at the site.
“The bottom line is this is all about improving efficiency, looking for ways to improve our carbon footprint, reduce greenhouse gases,” NewRange spokesman Bruce Richardson said in an interview. “If there’s a net environmental benefit, which is one of the end goals here, then it’s pretty hard to criticize.”
But environmental groups that have been fighting the project said the announcement is tantamount to an admission that the current mine plan is fundamentally flawed. They say mining the large untapped reserves of copper, nickel and platinum-group metals under northeastern Minnesota would pose unacceptable environmental risks because of the potential for acid mine drainage from the sulfide-bearing ore.
“PolyMet is rethinking every aspect of their mine plan after the courts have told them they have to do it,” Kathryn Hoffman, CEO of the Minnesota Center for Environmental Advocacy, said in an interview.
The studies in four key areas will look at alternative options for storing mine waste, for water treatment, for speeding up production and for reducing carbon emissions. Any major changes likely would be subject to additional environmental reviews and new permitting processes, which NewRange officials said would include opportunities for public comment and feedback. They stressed that nothing has been decided, and they said that they were announcing the studies in the interests of transparency for stakeholders, communities and tribes.
The current plan is to store the mine waste in the former LTV Steel iron mine tailings basin at the processing plant. Colin March, NewRange’s government and external affairs director, said in an interview that they will study whether a different design for the dam at the upgraded basin, or storing waste in old iron mine pits in the area, might have advantages.
They will also look at whether a conveyor system for transporting ore from the mine pit to the plant might make more environmental sense than the current plan for using diesel-powered trains, March said.
While the company contends the current plan for treating wastewater would meet the state’s stringent standards for protecting wild rice beds downstream, he said they will also study whether it is feasible to improve treatment even further.
And they are going to look at whether it would be advantageous to increase daily production from the currently planned 32,000 tons per day to 40,000 tons and run the mine for around 15 years instead of 20, without raising the total amount mined over its lifetime, March said. The idea would be a more efficient mine, not a bigger mine, he said.
The developers thought they had all the necessary state and federal permits in hand in 2018, but the project remains stalled by a series of court rulings. Its water pollution permit was sent back to the Minnesota Pollution Control Agency for more review. The overall permit to mine got sent back to the state Department of Natural Resources because of concerns about the waste basin design. And the Army Corps of Engineers revoked a wetlands destruction permit, saying it did not comply with the water quality standards set by a downstream tribe, so NewRange will have to apply for a new one to proceed.
“The fact that Minnesota regulators permitted this flawed project and have spent millions of needless dollars defending its misguided decision shows that our regulators have failed the citizens they are charged to protect,” Chris Knopf, executive director of Friends of the Boundary Waters Wilderness. said in a statement.
veryGood! (47)
Related
- Why Josh O'Connor Calls Sex Scenes Least Sexy Thing After Challengers With Zendaya and Mike Faist
- What to know about Simone Biles' husband, Chicago Bears safety Jonathan Owens
- Maine State Police investigate discovery of 3 bodies at a home
- Paris’ Olympics opening was wacky and wonderful — and upset bishops. Here’s why
- Pistons' Ausar Thompson cleared to play after missing 8 months with blood clot
- 2024 Olympics: Simone Biles Fights Through Calf Pain During Gymnastics Qualifiers
- Sonya Massey called police for help, 30 minutes later she was shot in the face: Timeline
- Drone-spying scandal: FIFA strips Canada of 6 points in Olympic women’s soccer, bans coaches 1 year
- FSU football fires offensive, defensive coordinators, wide receivers coach
- Irish sisters christen US warship bearing name of their brother, who was lauded for heroism
Ranking
- Mike Tyson concedes the role of villain to young foe in 58-year-old’s fight with Jake Paul
- Team USA men's water polo team went abroad to get better. Will it show at Paris Olympics?
- Grimes' Mom Accuses Elon Musk of Withholding Couple's 3 Kids From Visiting Dying Relative
- Why Alyssa Thomas’ Olympic debut for USA Basketball is so special: 'Really proud of her'
- 2025 Medicare Part B premium increase outpaces both Social Security COLA and inflation
- American Morelle McCane endured death of her brother during long road to Olympics
- Céline Dion's dazzling Olympics performance renders Kelly Clarkson speechless
- 2024 Paris Olympics highlight climate change's growing threat to athletes
Recommendation
-
Horoscopes Today, November 10, 2024
-
2024 Paris Olympics in primetime highlights, updates: Ledecky, Brody Malone star
-
Paris Olympics in primetime: Highlights, live updates, how to watch NBC replay tonight
-
Equestrian scandal leaves niche sport flat-footed in addressing it at Olympics
-
Judge hears case over Montana rule blocking trans residents from changing sex on birth certificate
-
American Morelle McCane endured death of her brother during long road to Olympics
-
Paris Olympics: Why Fries and Avocados Are Banned in the Olympic Village
-
How the Team USA vs. Australia swimming rivalry reignited before the 2024 Paris Olympics